blog

If exactly 3 projects are to be selected from a set of 5 projects, this would be written as 3 separate constraints in an integer program.

If exactly 3 projects are to be selected from a set of 5 projects, this would be written as 3 separate constraints in an integer program.

Question 1

If exactly 3 projects are to be selected from a set of 5 projects, this would be written as 3 separate constraints in an integer program.

Answer
True
False
2 points Save Answer
Question 2

Rounding non-integer solution values up to the nearest integer value will result in an infeasible solution to an integer linear programming problem.

Answer
True
False
2 points Save Answer
Question 3

A conditional constraint specifies the conditions under which variables are integers or real variables.

Answer
True
False
2 points Save Answer
Question 4

In a mixed integer model, some solution values for decision variables are integer and others are only 0 or 1.

Answer
True
False
2 points Save Answer
Question 5

If we are solving a 0-1 integer programming problem with three decision variables, the constraint x1 + x2 + x3 ≤ 3 is a mutually exclusive constraint.

Answer
True
False
2 points Save Answer
Question 6

If we are solving a 0-1 integer programming problem with three decision variables, the constraint x1 + x2 ≤ 1 is a mutually exclusive constraint.

Answer
True
False
2 points Save Answer
Question 7

If we are solving a 0-1 integer programming problem, the constraint x1 ≤ x2 is a __________ constraint.
Answer

multiple choice

mutually exclusive

conditional

corequisite
2 points Save Answer
Question 8

Max Z = 5×1 + 6×2
Subject to: 17×1 + 8×2 ≤ 136
3×1 + 4×2 ≤ 36
x1, x2 ≥ 0 and integer
What is the optimal solution?
Answer

x1 = 6, x2 = 4, Z = 54

x1 = 3, x2 = 6, Z = 51

x1 = 2, x2 = 6, Z = 46

x1 = 4, x2 = 6, Z = 56
2 points Save Answer
Question 9

Assume that we are using 0-1 integer programming model to solve a capital budgeting problem and xj = 1 if project j is selected and xj = 0, otherwise.
The constraint (x1 + x2 + x3 + x4 ≤ 2) means that __________ out of the 4 projects must be selected.
Answer

exactly 2

at least 2

at most 2

none of the above
2 points Save Answer
Question 10

The solution to the linear programming relaxation of a minimization problem will always be __________ the value of the integer programming minimization problem.
Answer

greater than or equal to

less than or equal to

equal to

different than

2 points Save Answer
Question 11

Binary variables are
Answer

0 or 1 only

any integer value

any continuous value

any negative integer value
2 points Save Answer
Question 12

In a 0-1 integer programming model, if the constraint x1-x2 ≤ 0, it means when project 2 is selected, project 1 __________ be selected.
Answer

must always

can sometimes

can never

A and B

2 points Save Answer
Question 13

If we are solving a 0-1 integer programming problem, the constraint x1 = x2 is a __________ constraint.
Answer

multiple choice

mutually exclusive

conditional

corequisite
2 points Save Answer
Question 14

You have been asked to select at least 3 out of 7 possible sites for oil exploration. Designate each site as S1, S2, S3, S4, S5, S6, and S7. The restrictions are:
Restriction 1. Evaluating sites S1 and S3 will prevent you from exploring site S7.
Restriction 2. Evaluating sites S2 or
S4 will prevent you from assessing site S5.
Restriction 3. Of all the sites, at least 3 should be assessed.
Assuming that Si is a binary variable, the constraint for the first restriction is
Answer

S1 + S3 + S7 ≥ 1

S1 + S3 + S7 ≤1

S1 + S3 + S7 = 2

S1 + S3 + S7 ≤ 2
2 points Save Answer
Question 15

If we are solving a 0-1 integer programming problem, the constraint x1 + x2 ≤ 1 is a __________ constraint.
Answer

multiple choice

mutually exclusive

conditional

corequisite
2 points Save Answer
Question 16

The Wiethoff Company has a contract to produce 10000 garden hoses for a customer. Wiethoff has 4 different machines that can produce this kind of hose. Because these machines are from different manufacturers and use differing technologies, their specifications are not the same.

Write the constraint that indicates they can purchase no more than 3 machines.
Answer

Y1 + Y2 + Y3+ Y4 ≤ 3

Y1 + Y2 + Y3+ Y4 = 3

Y1 + Y2 + Y3+ Y4 ≥3

none of the above

2 points Save Answer
Question 17

If the solution values of a linear program are rounded in order to obtain an integer solution, the solution is
Answer

always optimal and feasible

sometimes optimal and feasible

always optimal but not necessarily feasible

never optimal and feasible
2 points Save Answer
Question 18

The Wiethoff Company has a contract to produce 10000 garden hoses for a customer. Wiethoff has 4 different machines that can produce this kind of hose. Because these machines are from different manufacturers and use differing technologies, their specifications are not the same.

Write a constraint to ensure that if machine 4 is used, machine 1 will not be used.
Answer

Y1 + Y4 ≤ 0

Y1 + Y4 = 0

Y1 + Y4 ≤ 1

Y1 + Y4 ≥ 0
2 points Save Answer
Question 19

Max Z = 3×1 + 5×2
Subject to: 7×1 + 12×2 ≤ 136
3×1 + 5×2 ≤ 36
x1, x2 ≥ 0 and integer

Find the optimal solution. What is the value of the objective function at the optimal solution. Note: The answer will be an integer. Please give your answer as an integer without any decimal point. For example, 25.0 (twenty-five) would be written 25

Answer
2 points Save Answer
Question 20

Consider the following integer linear programming problem

Max Z = 3×1 + 2×2
Subject to: 3×1 + 5×2 ≤ 30
5×1 + 2×2 ≤ 28
x1 ≤ 8
x1 ,x2 ≥ 0 and integer

Find the optimal solution. What is the value of the objective function at the optimal solution. Note: The answer will be an integer. Please give your answer as an integer without any decimal point. For example, 25.0 (twenty-five) would be written 25

Answer

Is this the question you were looking for? If so, place your order here to get started!

×