blog

Progress Performance Measurement Evaluation & Managing Risk

Progress Performance Measurement Evaluation & Managing Risk

  1. How does earned value give a clearer picture of project schedule and cost status than a simple plan versus actual system?

 

  1. Schedule variance (SV) is in dollars and does not directly represent time. Why is it still useful?

 

 

  1. Project risks can/cannot be eliminated if the project is carefully planned.

 

  1. The chances of risk events occurring and their respective costs increasing change over the project life cycle. What is the significance of this phenomenon to a project manager?

 

 

Is this the question you were looking for? If so, place your order here to get started!

×